MSR&LHA color logo

Climax Locomotive S/N 1551 Restoration Project
 
Schedule of upcoming Climax Project work sessions
 
Background

Climax locomotive before restoration
The Climax locomotive sitting on the "dead line" in Cass prior to the start of restoration work in 2002.  (Photo by Sonny Burruss)  
Climax locomotive shop number 1551 was built by the Climax Locomotive Works in Corry, Pennsylvania, in 1919 and delivered new to the Moore-Keppel Company lumber operation in Ellamore (Randolph County) West Virginia.  It  operated there until the lumber mill closed in 1946.  It was then used as standby power on the coal hauling Middle Fork Railroad before being retired in 1960.  It was the one of the last Climax locomotives in U.S. commercial operation.

At retirement it was poorly maintained, badly worn and severely rusting.  It was destined for a proposed railroad museum to be built in Ellamore, but that project never got off the ground and the State purchased the locomotive in 1970.  It was trucked to Cass for restoration with a projected operational date of May, 1973.


Restoration work had just started when a massive fire destroyed the Cass shop complex in July, 1972.  Although there was some damage to the locomotive, it survived the shop fire in relatively good shape.  However, the loss of the shop caused an indefinite postponement of its restoration and work was never restarted.  The locomotive spent the next 30 years sitting on the Cass “dead line” awaiting its fate and slowly deteriorating in the weather.
Climax locomotive after restorationArtist's rendition of how the Climax locomotive will look after restoration is complete.  (Image by Richard Sparks)

In 1998 the Mountain State Railroad and Logging Historical Association proposed that the organization initiate a multi-year project to rebuild the locomotive and restore it to operational service in Cass.  The project was approved with the condition that a restoration building be built to reduce the project’s impact on the limited Cass shop facilities.  The Association solicited donations, completed a 40x100 foot building (which was turned over to the State), and commenced restoration work in October, 2002.

The Restoration Project


This is a complete mechanical restoration.  The locomotive was completely disassembled and each component analyzed to determine what needed to be done to restore it to operational condition.  Some parts just need to be cleaned and painted.  Others require welding, machining, or other significant repairs.  Some parts were beyond repair and are being used as patterns to fabricate replacements.  Many foundry patterns have made to allow accurate reproduction of unusable parts.

In all cases the goal is to maintain the historical integrity of the locomotive while restoring it to better than new condition so it will give years of reliable service without the need for major non-routine maintenance.  There is a core group of about a dozen volunteers with experience in machining and mechanical arts working on the project.  In addition, volunteers of varying skill levels are helping with various aspects of the project.

There is no firm date for completion of the project.  Work is progressing well, but since most volunteers live far from Cass there are a limited number of work sessions each year.  An unofficial goal is that the Climax may see some service around 2014, but that is far from a firm date.


Funding and Support

There are several sources of funding for the Project.  As of December, 2012, the Association and individual donors have provided over $196,000 in funding to purchase materials, tools, and contracted services.  The State of West Virginia obtained a $200,000 Federal grant for the project and that money is being used to purchase several big-ticket items such as axles, new steel tires, gear castings, injectors, and air compressors.  The Park already has a serviceable replacement boiler on hand that will be used after some repairs and certifications are completed.  Also, a number of companies have provided services and materials free or at significant discounts, and several have donated large machine tools to help equip the restoration facility.

Donations are always welcome and will help speed the restoration project.  All donations are tax deductible can can be sent to Bob Hoke, MSR&LHA Treasurer, 6304 Kaybro St., Laurel MD 20707.


Getting Involved

Working on the Climax locomotive
Restoration Project Leader Grady Smith assembling a repaired piston crosshead for the Climax locomotive. (Photo by Gerald Curtis)

Volunteers are always welcome to help with the project.  There are normally work session about every two or three weekends.  Dormitory-style housing is supplied in Cass at no cost  and meals are provided by the Association.  Workers typically arrive on Friday evening, work a long day on Saturday and Sunday morning with an early afternoon departure for home.  Due to insurance regulations all volunteers must be current MSR&LHA members and everyone must sign a liability waiver for the Park.

If you are interested in volunteering please contact Grady Smith, the Climax Restoration Project Manager, at loco@msrlha.org or 740-373-2895 to get the latest work schedule and discuss your interests and skills.

Check the Schedule of Upcoming Climax Project Work Sessions.


Summary of Some Recent Work Sessions


April 6-7, 2013Continued work on the brake rigging; applying the butt strap to the steam dome casing.
March 23-24, 2013Reaming brake hanger holes and brazing the worn ends of the front truck's bolster.
March 9-10, 2013Major work on the front truck, the new diamond stack, and both front and rear cut levers and grab rails.
February 23-24, 2013Inital assembly of front (final) truck, making a cut lever, swedging a bolt hole, making brake rod clevices
July 21-22, 2012Moving the 3rd truck into position under the tender frame
April 28-29, 2012Diamond stack construction; rear truck; shop overview photos
February 18-19, 2012 (2)Moving the almost-completed water tank lid
February 18-19, 2012Center plate grooving; final water tank welding & lifting pads; stack height calculations
February 4-5, 2012Constructing the sand dome
January 14-15, 2012 (3)Anatomy of a Shay smoke stack (compared to the Climax)
January 14-15, 2012 (2)Stack ring machine work
January 14-15, 2012Placing the tender tank top
November 19-20, 2011Fabricating a center pin; Stack ring work; Countershaft bracket truss rods; Water tank riser
April 30 - May 1, 2011 (3)Manufacturing babbet hammers
April 30 - May 1, 2011 (2)Tender truck gear assembly; Water tank welding; split washer & spacer machining
April 30 - May 1, 2011Installing tender truck gears & bolster; sand boxes; water tank bottom welding
April 16-17, 2011Gear shaft assembly; machining gear shaft; sandbox
April 9-10, 2011Truck assembly, ladder fabrication, water tank interior view
April 2-3, 2011Machining bearings
March  26-27, 2011Drilling front bolster and shaft machining
February 12-13, 2011Tank baffles & outlets; swivel plates; gear shafts
December 18, 2010(off site work session) Boring the Climax locomotive's pinion gears
November 20-21, 2010Tender tank; Climax ladder; center plates; misc. parts
November 13-14, 2010Cross box bearings; water tank trim; brake hanger holes
November 6, 2010Machining gear shaft bearings; miscellaneous activities.
October 9-10, 2010Various machining and welding activities; cleaning telltales on the boiler.
September 25-26, 2010Miscellaneous tasks (boiler, water tank trim, machining)
May 11, 2010Cross box boring
April 10-11, 2010Water tank baffle installation; Boiler thickness measurements
March 13-14, 2010"Before" locomotive photos; masking frame parts; machining work
February 20-21, 2010Truck assembly; thrust washer machining; grinding lapped cylinder seals
January 30-31, 2010Water tank fabrication and welding; Truck component bending
January 16-17, 2010Machining a bolster swivel plate; rebuilding an arch bar truck frame
November 21-22, 2009Wood work on tender tank decking; general machining
November 14-15, 2009Additional assembly of the tender truck; begin making water tank deck
November 7-8, 2009Initial (partial) assembly of the tender truck
October 31 - November 1, 2009Drill the new top bar for the truck frame; painting; bending bolster truss rods; brazing up a casting defect
October 2-4, 2009Sandblast and paint the frame and other parts
September 19-20, 2009prepare frame for sandblasting; move tender truck
February 2-3, 2008Coal bunker; lathe rebuilding; bolster swivel plates; water tank, shop views
January 19-20, 2008Coal bunker; pinion shaft removal; rear coupler pocket
January 5-6, 2008Frame repairs; horn/pinion gear work; center (swivel) plates
March 31 - April 1, 2007Horn machining
March 17-18, 2007Drawbar pocket; square shafts; horn welding; storage locker; main frame
March 3-4, 2007Square shafts; coal bunker; drawbar pocket; radial-arm saw
February 17-18, 2007Horn castings; Reed Prentice lathe, draw-bar pins; square shafts
January 20-21, 2007Crankshaft machining; tank frame work; main frame; square drive shafts
January 6-7, 2007Transport donated machine tools; delivery of repaired smoke box saddle; crankshaft machining

Return to the MSR&LHA Home page

Page last updated or validated on April 17, 2013